198 apartments in Bornstedter Feld in Potsdam

Bornstedter Feld, situated on the north side of Potsdam, is currently the town’s only residential development site. The MILA Group commissioned 198 new housing units here as part of the “Mies-van-der-Rohe-Strasse” project. Eighteen multi-family houses, distributed between seven different properties, have been ready for occupancy since spring 2017. The project also included three underground garages and eight commercial units.

Solution – MEAVECTOR & MEAMAX

MEAVECTOR concrete light wells and MEAMAX GRP light wells with a suitable mesh were chosen – in the AQUA version in each case. MILA also decided in favour of the MEACAPE light well cover as protection against rainwater from the façade or driving rain against the light well.

Verdict

The torrential rain which fell in Potsdam at the end of June 2017 (the heaviest rainfall since records began) was a chance for MEA’s AQUA solutions to prove that they provide reliable protection against water ingress. No damage whatsoever was reported due to leaking light wells.

At a glance

  • Place: Potsdam, Germany
  • Products:
    • MEAVECTOR AQUA concrete light well with closed floor and with/without drainage opening
    • MEAMAX AQUA GRP light well
    • MEALUXIT casement window system
    • 30/30 mesh
    • MEACAPE light well cover
Share this content:

More References from MEA

MONOLITHIC DRAINAGE SOLUTION FOR DHL BASE IN ALTENSTEIG

The MEADRAIN DM monolithic drainage channel was used to drain the logistics area of the DHL base in Altensteig, Baden-Württemberg.

Read more

Drainage of the new production area of the Bachl company in Paitzdorf

The MEACRET LINE 200 concrete slotted channel was used for the expansion of the Bachl company's production site in Paitzdorf.

Read more

Roadway drainage of the federal road B 87

The innovative 2-1 drainage solution MEAKERB was used for the rehabilitation of the B 87 federal road between Duben and Luckau.

Read more